CO129-518-8 Colonial Development Fund- requests and recommendations for monetary assistance for various projects 30-8-1929 - 28-2-1930 — Page 26

CO129 Colonial Office Hong Kong Records 理藩院香港檔案 All

(1)

Hong Kong.

SUMMARY OF ANSWERS TO "SCHEDULED QUESTIONS"

26

1. Description.

2. Estimated

Total Cost.

3. Date of

4.

Commencement.

Date of Completion.

5. Allocation of

Cost.

6.

Reasons for not under- taking work

before.

7. Method of

financing.

8. Advantages.

9.

Detailed Estimates.

10. Assistance

desired under

Act.

11. Security for

advances to non-official

concerns.

(a) Aberdeen Valley Water Scheme;

(b) Sheng-mur. Water Scheme.

To provide adequate supplies for the

increasing population of Hong Kong Island

and the mainland territory of Kowloon.

(a) $2.702.000

(b) $4.158.509

(a) Uncertain. (b) 1923.

No information available.

£270,200 approximately

£415.850 approximately

(a) Orders for £34,090 in United Kingdom

already placed.

(b)Orders for £15,470

do.

do.

No information available as to allocation

of future expenditure.

Work is already in progress.

The Sheng-nun scheme has been hitherto

financed by local loan at 6%. Future works

are to be paid from Current revenue or surplus

balances pending reimbursement from further loan

See (1) above. No estimate of revenue to

be earned is available.

Have been prepared.

Loan of £49,560 (value of orders in United

Kingdom) on easiest possible terms. No sugges- tion is made as to the terms of repayment.

Does not arise.